What Should Be Included in a Solar Installation Contract?

Solar100 Malaysia Solar Contract Guide

What Should Be Included in a Solar Installation Contract?

Updated: July 2026

A solar installation contract should explain exactly who is responsible for the project, what system will be supplied, which services and fees are included, how the installation will be carried out, when payments become due and what happens if the design, equipment, approval, timeline, workmanship or warranty outcome changes.

Quick Answer The contract should identify the legal contracting company, customer and project address; state the exact panel and inverter models, quantities, DC and AC capacities and system design; define the full project scope, application work, exclusions, price, taxes and payment milestones; explain roof, electrical, safety, testing, commissioning and handover responsibilities; and include written equipment warranties, workmanship coverage, roof-leak responsibility, warranty-labour terms, after-sales response, cancellation rights, delay provisions and dispute procedures.
SEDA-Related Standards Review
SSM Registration Information Review
Policy & Application Process Review
After-Sales Support Assessment
Consultation & Quotation Comparison

Which Contracting Parties Should Be Identified?

The agreement should clearly identify the customer, legal contracting company and every technical or subcontracted party responsible for a material part of the project.

  • Customer’s full legal name
  • Customer’s identification or company details
  • Electricity-account holder
  • Installation-property address
  • Legal name of contracting company
  • SSM registration number
  • Registered business address
  • Company contact details
  • Named project representative
  • Named after-sales representative
  • Responsible RPVSP, where applicable
  • Registered electrical contractor
  • Relevant competent person
  • Engineering consultant, where required
  • Subcontractors performing material work
  • Equipment supplier or distributor

Contracting Company

The entity signing the agreement should be clearly connected to the quotation, invoice, payment account and warranty obligations.

Technical Parties

The agreement should identify who designs, supervises, installs, tests, commissions and certifies the electrical work.

Subcontractors

The main contractor should remain responsible for subcontracted work unless the contract clearly and lawfully provides otherwise.

Customer Contact

The correct customer email, telephone number and electricity-account information should be used for applications and project notices.

Check Who Receives the Money: The legal contracting entity, invoice issuer and payment-account holder should normally be consistent. Any difference should be explained and documented before payment.

Which Solar System Specifications Should Be Written into the Contract?

The contract should define the exact system being purchased. General descriptions such as “premium panels” or “high-efficiency inverter” are not sufficient.

System Item Contract Details Required
Solar Panels Manufacturer, exact model, quantity, wattage per panel, total DC capacity, product warranty and performance warranty
Solar Inverter Manufacturer, exact model, quantity, rated AC capacity, phase, MPPT configuration, monitoring and warranty
Battery, If Included Manufacturer, model, nominal and usable capacity, charging power, backup arrangement, operating modes and warranty
Mounting System Rail, clamp, fastener and roof-attachment materials, corrosion protection and waterproofing method
Electrical Protection Isolators, breakers, surge protection, earthing, enclosures, labels and connection arrangement
Monitoring Equipment Application, portal, data logger, energy meter, current sensors, account access and subscription terms
System Design Panel layout, string design, MPPT allocation, single-line diagram, interconnection point and cable routes
  • Total panel DC capacity
  • Total inverter AC capacity
  • DC-to-AC ratio
  • Single-phase or three-phase design
  • Panel layout
  • Panel orientation
  • Panel tilt, where relevant
  • String arrangement
  • MPPT allocation
  • Inverter installation location
  • Connection point
  • Protection arrangement
  • Monitoring scope
  • Battery and backup scope
  • Export-control arrangement
  • Future expansion limitations
Equipment Substitutions Must Be Controlled: The contract should state whether substitutions are permitted, what technical standard an alternative must meet and when the customer’s prior written approval is required.

What Should Be Included in the Solar Project Scope?

The scope should explain every service included in the agreed price and identify every foreseeable exclusion that may result in an additional charge.

1

Site Assessment

Inspect the roof, electrical installation, shading, access, connection point and proposed equipment locations.

2

System Design

Prepare the panel layout, string design, protection arrangement, calculations and required engineering documents.

3

Application Work

Prepare, submit and follow up the applicable Solar ATAP, technical, licensing, meter and utility documents.

4

Equipment Supply

Supply the specified panels, inverter, mounting, protection, monitoring and optional battery equipment.

5

Installation

Complete roof, mounting, cabling, electrical, labelling, access and protection work.

6

Testing and Handover

Test, commission, document and demonstrate the completed system before final acceptance.

  • Site visit and measurements
  • Roof-condition review
  • Shading assessment
  • Electrical-system inspection
  • System design
  • Engineering calculations
  • Application preparation
  • Application follow-up
  • Equipment procurement
  • Delivery and storage
  • Scaffolding or lifting equipment
  • Roof mounting
  • DC cabling
  • AC cabling
  • Protection and earthing
  • Meter or switchboard work
  • Monitoring configuration
  • Testing and commissioning
  • Customer training
  • Final documentation
Included Scope Should Be Specific: Statements such as “complete installation” should be supported by a detailed schedule describing the work, equipment, fees, documents and customer responsibilities.

Which Exclusions and Additional Costs Should Be Listed?

Possible Exclusion What the Contract Should Explain
Technical Assessment Whether CCC, CAS, PSS or another study is required, who appoints the provider and who pays the fee
Roof Repair Existing defects, replacement of damaged materials, waterproofing outside the solar work and structural reinforcement
Electrical Upgrade Main switchboard, distribution board, meter board, cable, protection or earthing modifications
Access Equipment Scaffolding, mobile platform, crane, lifting, traffic management or restricted-access charges
Utility Charges Application, meter, connection, study, testing or other third-party charges
Communication Equipment Wi-Fi extension, Ethernet work, mobile-data plan, monitoring subscription or replacement logger
Future Service Cleaning, inspection, preventive maintenance, fault diagnosis and out-of-warranty attendance
An Exclusion May Still Be Necessary: Work excluded from the fixed price may still have to be completed before the project can be safely installed, commissioned, approved or operated.

What Application and Approval Responsibilities Should Be Included?

The contract should define which programme or operating arrangement is proposed, which party prepares each submission and what happens if the application is delayed, returned, approved at a lower capacity or rejected.

  • Applicable solar programme
  • Application applicant
  • Responsible submitting party
  • Required customer documents
  • Required technical documents
  • Technical-assessment responsibility
  • Application fees
  • Utility fees
  • Generating-licence responsibility, if applicable
  • Registered electrical-contractor documents
  • Competent-person documents
  • Form G and Form H responsibility
  • Single-line diagram
  • Test results
  • Testing and commissioning form
  • Meter or contract coordination
  • Response to application queries
  • Document-correction responsibility
  • Approval condition management
  • Application handover to customer
Customer Documents The contract should list the identification, company, electricity account, authorisation and property documents the customer must provide.
Provider Documents The provider should be responsible for the technical drawings, certificates, test records and contractor documentation included in its scope.
Approval Outcome The agreement should explain the options if the approved system capacity is lower than the proposed capacity.
Application Failure Refunds, deductions and customer cancellation rights should be stated if the project cannot proceed.
Approval Should Not Be Treated as Guaranteed: Official review, technical feasibility, document completeness and programme conditions may affect approval and the permitted system capacity.

What Roof and Structural Terms Should Be Included?

The contract should distinguish existing roof defects from damage caused by the solar work and clearly allocate responsibility for inspection, mounting, waterproofing, repair and future removal.

  • Existing roof material
  • Estimated roof age
  • Existing cracks or leaks
  • Existing corrosion
  • Damaged tiles or sheets
  • Pre-installation photographs
  • Structural-assessment requirement
  • Roof-load assumptions
  • Mounting method
  • Roof-penetration method
  • Flashing and sealing method
  • Corrosion protection
  • Wind-load consideration
  • Drainage clearance
  • Maintenance access
  • Roof-leak warranty
  • Damage-repair responsibility
  • Removal and reinstallation cost
Roof Issue Contract Requirement
Existing Defect Record the condition and state whether repair is required before installation
Installation Damage Identify who repairs damaged tiles, sheets, membranes, gutters, ceilings or structural components
Roof Leakage Define the covered causes, response time, investigation process, warranty period and exclusions
Future Roof Work Explain who pays to remove, store, reinstall and recommission the solar equipment
Use a Pre-Installation Condition Record: Photographs and written observations reduce later disputes about whether a roof defect existed before the solar installation.

What Electrical and Safety Responsibilities Should Be Included?

The agreement should identify the responsible electrical contractor and competent personnel, define the protection system and state who certifies the completed installation.

  • Responsible electrical contractor
  • Responsible competent person
  • Electrical design scope
  • DC isolators
  • AC isolators
  • Circuit breakers
  • Surge-protection devices
  • Earthing and bonding
  • Cable type and size
  • Cable support and containment
  • Connector compatibility
  • Weatherproof enclosures
  • Equipment labels
  • Emergency shutdown information
  • Safe access requirements
  • Testing responsibility
  • Certification responsibility
  • Defect-correction responsibility
Electrical Work Requires Appropriate Responsibility: The contract should not leave the design, supervision, testing or certification of electrical work to unidentified or unqualified parties.

What Price and Payment Terms Should Be Included?

The contract should state the complete agreed price, identify taxes and third-party fees and connect each payment to a clearly defined project milestone.

Payment Stage Possible Milestone Evidence to Require
Deposit Contract execution and project initiation Signed agreement, receipt and refund conditions
Application Payment Application documents completed or submitted Submission confirmation and fee breakdown
Equipment Payment Equipment ordered, reserved or delivered Models, quantities, delivery record and ownership terms
Installation Payment Physical installation substantially completed Inspection, progress record and outstanding-work list
Final Payment Testing, commissioning and handover completed Operational system, certificates, warranties and complete handover documents
  • Total contract price
  • Applicable taxes
  • Official fees included
  • Official fees excluded
  • Technical-study fees
  • Utility charges
  • Deposit amount
  • Progress-payment amounts
  • Payment due dates
  • Milestone definitions
  • Invoice requirements
  • Refund conditions
  • Retention amount
  • Late-payment charges
  • Financing charges
  • Price-adjustment conditions
  • Variation-order procedure
  • Quotation-validity period
Payment Should Follow Verifiable Progress: Avoid unclear schedules that require most of the contract price before equipment delivery, completed installation, testing, commissioning and customer handover.

What Timeline and Delay Terms Should Be Included?

The project schedule should distinguish estimated regulatory or utility timing from work controlled by the installer.

  • Contract commencement date
  • Customer-document deadline
  • Site-assessment date
  • Design-completion date
  • Application-submission target
  • Equipment-order date
  • Expected delivery period
  • Installation notice period
  • Installation duration
  • Testing date
  • Commissioning date
  • Handover date
  • Completion definition
  • Permitted extensions
  • Customer-caused delays
  • Installer-caused delays
  • Third-party delays
  • Delay-notice requirements
  • Delay remedies
  • Termination threshold
Physical Installation Complete Panels and equipment are installed, but testing, approval, meter work or commercial operation may still be outstanding.
Project Fully Complete The system has been tested, commissioned, documented, handed over and made operational under the agreed arrangement.
Define “Completion” Clearly: A system being mounted on the roof does not necessarily mean that the project has been tested, commissioned, approved, documented and placed into operation.

What Testing, Commissioning and Handover Terms Should Be Included?

The contract should state which inspections and tests will be completed, who signs the documents and what the customer must receive before final acceptance.

1

Visual Inspection

Check mounting, cable routes, labels, clearances, weather protection and visible workmanship.

2

Electrical Testing

Complete the applicable continuity, polarity, insulation, earthing, protection and operational tests.

3

Commission the Equipment

Configure the inverter, protection settings, meter, monitoring, battery and operating arrangement.

4

Confirm Operation

Verify generation, monitoring, import and export measurement, battery operation and alarms where included.

5

Correct Defects

Record incomplete or defective work and define the correction deadline before final acceptance.

6

Complete Handover

Transfer system documents, monitoring access, warranties, operating instructions and support contacts.

  • Final panel layout
  • Final single-line diagram
  • As-built cable routes
  • Equipment datasheets
  • Panel serial numbers
  • Inverter serial numbers
  • Battery serial numbers, if applicable
  • Test results
  • Testing and commissioning records
  • Completion certificates
  • Application documents
  • Approval documents
  • Equipment warranties
  • Workmanship warranty
  • Roof-leak warranty
  • Monitoring-owner access
  • Operating instructions
  • Emergency shutdown instructions
  • Maintenance recommendations
  • After-sales contacts
Make Complete Handover a Final-Payment Condition: Important certificates, warranty documents, serial numbers and monitoring access are usually easier to obtain before the contract price has been paid in full.

What Warranties and After-Sales Terms Should Be Included?

Warranty Area Contract Details Required
Panel Product Warranty Period, covered defects, registration, claim process and replacement basis
Panel Performance Warranty Degradation schedule, testing method, claim conditions and remedy
Inverter Warranty Period, local representative, repair or replacement process and expected lead time
Battery Warranty Period, cycle or energy limits, usable-capacity conditions and operating exclusions
Workmanship Warranty Mounting, cabling, electrical work, weather sealing, defects and correction obligations
Roof-Leak Warranty Covered leaks, investigation process, response period, repair responsibility and exclusions
Warranty Labour Diagnosis, travel, transport, access equipment, removal and reinstallation
After-Sales Support Support channel, acknowledgement time, remote diagnosis, site-visit target and applicable charges
  • Warranty start date
  • Warranty registration responsibility
  • Warranty certificate delivery
  • Claim-submission responsibility
  • Fault-diagnosis responsibility
  • Site-visit charge
  • Transport charge
  • Scaffolding charge
  • Removal labour
  • Reinstallation labour
  • Replacement-equipment ownership
  • Replacement lead time
  • Temporary replacement availability
  • Monitoring support
  • Firmware-update responsibility
  • Preventive-maintenance scope
  • Support escalation process
  • Installer-closure arrangement
Manufacturer Warranty Does Not Automatically Include Labour: The contract should state who pays for diagnosis, transport, roof access, equipment removal and reinstallation when a component fails.

Should Generation and Savings Estimates Be Included?

A proposal may include estimated annual generation, electricity savings and payback. The contract should distinguish estimates from guarantees and identify the assumptions used.

  • Estimated annual generation
  • Solar-resource assumption
  • Roof-orientation assumption
  • Shading assumption
  • Temperature losses
  • Soiling losses
  • Cable and inverter losses
  • System availability
  • Annual degradation
  • Self-consumption assumption
  • Export assumption
  • Tariff assumption
  • Tariff-inflation assumption
  • Maintenance-cost assumption
  • Replacement-cost assumption
  • Payback-calculation method
Forecasts Should Be Supported, Not Overstated: Weather, electricity use, tariffs, export treatment, equipment downtime, degradation and maintenance may cause actual results to differ.

What Change, Cancellation and Termination Terms Should Be Included?

The agreement should explain how changes are approved, how additional costs are calculated and when either party may cancel or terminate the project.

  • Written variation-order requirement
  • Customer approval requirement
  • Price-adjustment method
  • Timeline-adjustment method
  • Equipment-substitution procedure
  • Design-change procedure
  • Lower approved-capacity procedure
  • Application-rejection procedure
  • Customer cancellation rights
  • Installer cancellation rights
  • Refund calculation
  • Non-refundable cost definition
  • Material-breach definition
  • Defect-correction period
  • Termination notice
  • Equipment ownership after termination
  • Removal responsibility
  • Roof-restoration responsibility
  • Document-transfer responsibility
  • Dispute-resolution procedure
Variation Order No additional work should be charged without a written description, price, timeline effect and authorised approval.
Equipment Substitution A replacement model should meet documented technical, warranty and compatibility requirements.
Cancellation The agreement should identify which actual costs may be deducted and what evidence must be provided.
Dispute Resolution The escalation process, governing law and relevant jurisdiction should be stated.
Do Not Leave Material Terms Blank: Missing equipment models, dates, payment triggers, warranty periods or responsibilities may create avoidable disputes after the agreement is signed.

Which Customer Responsibilities Should Be Included?

  • Provide accurate electricity bills
  • Provide account-holder documents
  • Provide company documents, where relevant
  • Provide property-access permission
  • Disclose known roof defects
  • Disclose planned renovations
  • Provide internet access, if required
  • Provide safe site access
  • Obtain landlord consent, if required
  • Obtain management consent, if required
  • Respond to document requests
  • Approve drawings or variations
  • Make milestone payments
  • Protect delivered equipment, where agreed
  • Follow operating instructions
  • Report faults promptly
  • Maintain monitoring credentials
  • Arrange future maintenance
Customer Duties Should Be Reasonable and Specific: The contract should not transfer responsibility for the installer’s design, electrical work, workmanship or certification to the customer.

What Contract Questions Should You Ask Before Signing?

  1. What is the exact legal name of the contracting company?
  2. Does the company name match the quotation, invoice and bank account?
  3. Who is the responsible RPVSP, where applicable?
  4. Which registered electrical contractor will perform the work?
  5. Which competent person will supervise or certify the installation?
  6. What are the exact panel and inverter models?
  7. What are the total DC and AC capacities?
  8. Can any equipment be substituted without my written approval?
  9. Which design and engineering services are included?
  10. Which application services are included?
  11. Which official fees are included?
  12. Which technical-study costs are excluded?
  13. Which roof repairs are excluded?
  14. Which electrical upgrades are excluded?
  15. Is scaffolding or lifting equipment included?
  16. Who is responsible if the roof leaks?
  17. How long is the workmanship warranty?
  18. Does equipment warranty include replacement labour?
  19. What project milestone triggers each payment?
  20. Is any final payment retained until complete handover?
  21. What happens if the application is rejected?
  22. What happens if only a lower capacity is approved?
  23. What happens if the specified equipment is unavailable?
  24. What happens if the installer misses the agreed timeline?
  25. Which documents will I receive at handover?
  26. Will I receive permanent monitoring-owner access?
  27. Who handles future warranty claims?
  28. What are the cancellation and refund conditions?
  29. How are disputes escalated?
  30. Which terms continue after project completion?

Final Solar Installation Contract Checklist

  • Legal company identified
  • SSM details checked
  • Customer and property identified
  • Technical parties identified
  • Exact panel model stated
  • Exact inverter model stated
  • DC and AC capacity stated
  • System layout included
  • Complete scope listed
  • Exclusions listed
  • Application responsibility stated
  • Official fees stated
  • Technical-study responsibility stated
  • Roof condition recorded
  • Roof damage responsibility stated
  • Electrical responsibility stated
  • Payment milestones defined
  • Project timeline defined
  • Completion definition stated
  • Testing requirements listed
  • Handover documents listed
  • Workmanship warranty stated
  • Warranty labour stated
  • After-sales support stated
  • Variation procedure stated
  • Cancellation terms stated
  • Refund terms stated
  • Dispute procedure stated

What Is Solar100’s Role in Solar Contract Comparison?

Solar100

  • Supports solar-provider discovery
  • Helps customers organise initial project information
  • Supports initial quotation comparison
  • Helps identify differences in contract scope
  • Provides general contract-checklist information
  • Does not prepare legal or engineering documents
  • Does not approve or sign the installation contract
  • Does not guarantee contract performance

Selected Solar Provider

  • Assesss the property and electricity account
  • Prepares the project-specific quotation and contract
  • Defines the proposed system and equipment
  • Coordinates applicable applications and technical work
  • Performs or coordinates installation and commissioning
  • Provides the agreed warranties and after-sales support
  • Remains responsible for its written contractual commitments
  • Corrects applicable defects within the agreed scope

Frequently Asked Questions

What is the most important part of a solar installation contract?

The contract should clearly define the exact system, complete project scope, price, payment milestones, responsibilities, warranties, exclusions and remedies if the project does not proceed as expected.

Should the exact panel and inverter models be stated?

Yes. The manufacturer, exact model, quantity, capacity and applicable warranty should be written into the contract or a binding equipment schedule.

Should Solar ATAP application work be included in the contract?

The agreement should state whether the provider prepares and coordinates the applicable application, technical documents, testing records, contractor documents, forms, fees and follow-up work.

Should I pay the full solar price before installation?

Payment stages should generally follow documented project progress. Customers should understand what equipment, work, testing and handover must be completed before each payment becomes due.

Should roof-leak responsibility be written into the contract?

Yes. The agreement should distinguish existing roof defects from installation-related damage and define the coverage period, response process, repair responsibility and exclusions.

Does the equipment warranty automatically include labour?

No. Diagnosis, transport, roof access, removal and reinstallation may be excluded unless the contract provides specific labour coverage.

What happens if the approved system capacity is lower?

The contract should explain whether the design and price will be revised, whether the customer may cancel and which actual costs may be deducted.

What documents should I receive after installation?

Handover should normally include final drawings, equipment details, serial numbers, test and commissioning records, approvals, warranties, monitoring access, operating instructions and support contacts.

Can the installer replace equipment after I sign?

The contract should define when substitutions are allowed and require prior written customer approval for material changes to equipment, performance, compatibility or warranty.

Does Solar100 review or approve solar contracts?

Solar100 provides general provider-discovery and quotation-comparison support. It does not provide legal approval, engineering certification or a guarantee of contract performance.

The information on this page is provided for general educational and comparison purposes. It is not legal advice, contract drafting, engineering design, electrical certification, financial advice, application approval, installer endorsement, warranty approval or a guarantee of project completion, generation, savings, workmanship or dispute outcomes. Contract requirements, programme procedures, forms, official fees, registration status, licensing requirements, technical standards and utility processes may change and may differ according to the project. Customers should obtain the complete written agreement, verify the legal company and responsible technical parties, review current official requirements and seek independent legal or technical advice where appropriate. Solar100 is a provider-discovery and quotation-comparison platform. It is not the installer, electrical contractor, competent person, engineer, equipment manufacturer, warranty provider, electricity utility, regulator, lawyer, insurer, lender or approving authority and does not guarantee contractual performance, approval, equipment availability, warranty outcomes or after-sales service.

Compare Solar Contract Scope and System Quotations

Send your recent electricity bills, property location, proposed system size, panel and inverter models, existing quotations, payment schedule, warranty terms and exclusions to begin comparing solar proposals and contract scope from participating providers that may serve your area.

Request and Compare Solar Quotes

Jul 29,2026